Purpose
In order to meet the requirements of Directive 2014/94/EU of the European Parliament and of the Council on the deployment of alternative fuels infrastructure (Alternative Fuels Infrastructure Directive - AFID), the Federal Government's Climate Protection Program 2030 and the strategic further development of electromobility in the Free State of Bavaria, the establishment of a nationwide basic charging infrastructure of publicly accessible charging points is a mandatory requirement.
Object
The object of the funding is the procurement and construction of publicly accessible charging infrastructure for electric vehicles in Bavaria with at least one charging point, including the necessary grid connection.
In addition to the procurement and construction of charging infrastructure at new locations, funding is also provided for the upgrading or replacement of charging infrastructure and the upgrading of the grid connection at existing locations, provided that these have not already been funded and if added value can be demonstrated.
Funding is also provided for the connection of the funded charging points to the low or medium voltage grid and the combination of grid connection and a buffer storage tank if it serves to supply charging points.
Recipients of funding
Natural and legal persons, in particular municipalities and districts, are eligible to apply, provided that no restriction is made in the respective call for funding.
Type and scope, amount of the grant
Charging points and grid connections are funded with a maximum percentage share of 60%. The specific applicable funding rate will be announced in the respective funding call.
A maximum funding amount is also specified. For charging points, this depends on the charging capacity and is between EUR 2,500 and EUR 20,000. For grid connections, the maximum amount is EUR 10,000 or EUR 100,000.