Construction project; advance notice of the establishment of a construction site

As a rule, construction sites must be notified in advance to the responsible industrial inspectorate or mining authority in the form of an advance notice.

Description

The construction site pre-announcement must be prepared by the client or a commissioned third party (e.g. architect).

It must contain at least the following information:

  • Location of the construction site
  • Name and address of the building owner
  • Type of construction project
  • name and address of the third party responsible in place of the client
  • the name and address of the coordinator
  • estimated starting date and duration of the work
  • the maximum number of persons expected to be employed on the site
  • the number of employers and contractors without employees expected to work on the site
  • indication of the employers and contractors without employees already selected

Prerequisites

If you want to set up a construction site and it fulfils the following requirements, you must send an advance notice of the construction site to the trade supervisory office or mining office responsible for the location of the construction site. The mining office is responsible, among other things, if the construction project is subject to mining supervision or if it involves an underground cavity construction (tunnel, pressing or similar).

Prerequisites for the transmission of a construction site advance notice:

  • expected duration more than 30 working days and number of employees working at the same time more than 20
    or
  • the extent of the work is expected to exceed 500 person-days (e.g. if 5 employees will be working for more than 100 days).

Procedure

The advance notice must be sent to the trade supervisory office or mining office responsible for the location of the construction site.

Special notes

The advance notice shall be visibly displayed at the construction site.

In the event of significant changes, the advance notice shall be adapted.

A coordinator must be appointed for construction sites where employees of several employers are working - regardless of whether at the same time or one after the other.

In accordance with the Construction Site Ordinance, it must be checked whether a safety and health protection plan is to be drawn up before the construction site is set up.

Deadlines

The advance notice must be sent to the trade supervisory office or mining office responsible for the location of the construction site at least 2 weeks before the construction site is set up.

Required documents

  • health and safety plan, if applicable

Online procedures

  • Baustelle - Vorankündigung online

    Before setting up a construction site, you can send the responsible trade supervisory office or the responsible mining office the advance notice in accordance with § 2 of the Construction Site Ordinance online.

Status: 03.11.2021

Responsible for editing: Bayerisches Staatsministerium für Familie, Arbeit und Soziales

Contains machine translated content. Show the original content

  • Online transactions, Bavaria-wide
  • Online transactions, locally limited
  • Prefillable Form, Bavaria-wide
  • Legal bases, Bavaria-wide
  • Legal bases, locally limited
  • Fees, Bavaria-wide
  • Fees, locally limited